ASPICE MAN.3 – Project Management: Simple BP-Wise Guide for Delivery Team Audits


ASPICE MAN.3 – Project Management: Simple BP-Wise Guide for Delivery Team Audits

ASPICE audits can sometimes feel complicated because of the terminology and process language. But MAN.3 – Project Management becomes much easier if we translate each Base Practice (BP) into three simple questions:

What should the team do? → What evidence should I see? → What should I ask?

This article provides a simple, practical guide that delivery managers, project managers, technical program managers, Agile coaches, and ASPICE auditors can use during an internal audit.

Note: Always align the BP numbering and wording with the specific Automotive SPICE version and process model used by your organization.


What is ASPICE MAN.3?

MAN.3 – Project Management focuses on planning, executing, monitoring, and controlling the project so that project objectives can be achieved.

In simple terms:

MAN.3 ensures that the project is properly planned, monitored, risks and issues are managed, dependencies are controlled, and corrective actions are taken when required.


ASPICE MAN.3 – BP-wise Simple Explanation

BPSimple MeaningExpected EvidenceSimple Audit Question
BP1Define project scopeProject scope, boundaries, deliverables“Show me the approved project scope. What is in and out of scope?”
BP2Define project activities and tasksWBS, project plan, activities and tasks“How did you break the project into activities and tasks?”
BP3Estimate effort and resourcesEffort estimates, resource/capacity plan“How did you estimate effort and team capacity?”
BP4Define project scheduleSchedule, milestones, release plan“Show me the project schedule and key milestones.”
BP5Monitor project progressStatus reports, dashboards, KPI trends“How do you know whether the project is on track?”
BP6Manage project risksRisk register, mitigation plans“Show me your top risks and mitigation actions.”
BP7Manage project issuesIssue tracker, escalation records“Show me a major issue and how it was resolved.”
BP8Manage changesChange requests, impact analysis, approvals“Show me a recent change and its impact.”
BP9Ensure communicationStatus reports, meeting minutes, communication records“How do you ensure stakeholders receive project status?”
BP10Manage stakeholdersStakeholder list, RACI, communication plan“Who are your key stakeholders?”
BP11Manage interfaces and dependenciesDependency tracker, interface records“Show me your critical dependencies and how they are tracked.”
BP12Manage project qualityQuality plan, reviews, quality metrics“How do you know project quality expectations are being met?”
BP13Conduct project reviewsSteering reviews, milestone reviews, action items“Show me evidence of project reviews and decisions.”

How Should You Audit MAN.3?

A good audit should go beyond checking whether a document exists.

I recommend using the 4E approach:

1. Expectation

Understand what the team is expected to do.

Example:

Does the project have a defined approach for identifying and managing risks?

2. Evidence

Ask the team to show the actual evidence.

For risk management, this could include:

  • Risk register

  • Risk owner

  • Probability and impact

  • Mitigation action

  • Target date

  • Current status

3. Execution

Don't stop at the document.

Pick one real example and ask:

“Walk me through this risk from identification to closure.”

This helps you verify whether the process is actually being followed.

4. Effectiveness

Finally, ask:

“What happened after the mitigation? Did the risk exposure actually reduce?”

This is where you move from process compliance to process effectiveness.


Example: Auditing Risk Management

Let's take BP6 – Risk Management as an example.

Auditor Question 1

“Show me your current project risk register.”

Check whether risks have:

  • Description

  • Owner

  • Probability

  • Impact

  • Priority

  • Mitigation

  • Due date

  • Status

Auditor Question 2

“Show me your top three risks.”

Don't accept only the risk names.

Ask:

“Why is this a top risk?”

Auditor Question 3

“Who owns this risk?”

There should be a clear owner.

Auditor Question 4

“What mitigation action has been taken?”

Look for actual actions rather than statements such as:

“Team is monitoring.”

Auditor Question 5

“How do you know the mitigation was effective?”

This helps demonstrate that risk management is actively performed.


Most Important MAN.3 Evidence

For a delivery team, I would expect to see a connected chain of evidence:

Project Scope

↓

WBS / Activities

↓

Effort & Resource Plan

↓

Schedule & Milestones

↓

Risks & Dependencies

↓

Execution Tracking

↓

Status & KPI Monitoring

↓

Issues & Changes

↓

Project Reviews

↓

Corrective Actions

The important thing is not just having these documents.

The auditor should be able to trace the project story from planning to execution and corrective action.


10 Powerful MAN.3 Audit Questions

If you have limited time during an internal audit, these questions can give you a very good picture of project management maturity.

1. What exactly is your project scope?

2. What are your major deliverables and milestones?

3. How did you estimate effort and resources?

4. What is your current schedule status versus the baseline?

5. What are your top three project risks?

6. What are your critical cross-team dependencies?

7. Show me one major issue and explain how it was resolved.

8. Show me one recent change and its impact analysis.

9. What project metrics are you monitoring?

10. Show me a project review where management took a decision based on project data.


How to Write a Good ASPICE Audit Finding

Avoid vague findings such as:

❌ “Risk management is not good.”

Instead, make your finding specific and evidence-based.

Weak Finding

Risk management is not effective.

Better Finding

The project maintains a risk register; however, three high-priority risks do not have documented mitigation owners or target completion dates. Therefore, active risk treatment cannot be demonstrated.

This type of finding is:

  • Specific

  • Evidence-based

  • Traceable

  • Easier to understand

  • Easier to correct


A Simple Rule for Delivery Teams

One rule I recommend every Project Manager, Engineering Manager, and Technical Program Manager remember is:

“Don't tell me that you manage the project. Show me the evidence that proves you manage it.”

For MAN.3, strong evidence is not just a document.

It is the connection between:

Plan → Execute → Monitor → Identify Deviation → Take Action → Verify Outcome

That is what makes project management demonstrable during an ASPICE audit.


Final Takeaway

ASPICE MAN.3 is essentially about controlled project execution.

A mature project should be able to answer five simple questions:

Where are we going?
→ Scope & objectives

How will we get there?
→ Activities, resources & schedule

What could go wrong?
→ Risks, issues & dependencies

How do we know we are on track?
→ Metrics & monitoring

What do we do when things change?
→ Corrective actions & change management

If your delivery team can demonstrate these five areas with objective evidence, you are in a much stronger position for an ASPICE MAN.3 assessment.

#ASPICE #AutomotiveSPICE #MAN3 #ProjectManagement #SoftwareEngineering #AutomotiveSoftware #Agile #TechnicalProgramManagement #TPM #ProcessImprovement 

Comments

Popular posts from this blog

What Is Agentic AI? A Deep-Dive Explanation

AI Governance

Why Strategic Leadership Matters More After 20 Years